VOL XXIII, NO 7

Belzona® Anchors The Track

 
 

Industry:

General Industry (GIND)

 
 

Application:

Floor Problem Areas (FPA)

 
 

Customer Location:

Steel Plant, North Alabama USA

 
 

Application Date:

2002

 
 

Application Situation:

Grout had failed around the blast furnace rails

 
 

Problem:

Grout had to achieve high compressive strength in short outage time

 
 

Products:

Belzona® 4111 (Magma Quartz)
 

Substrate:

Concrete and Steel

 
 

Application Method:

Application was carried out in accordance with modified Belzona Know-How System Leaflet FPA-10. The old grout was removed and the rail was alligned and shimmed. A slurry mix of Belzona® 4111 was poured the length of the tract.

 
 

Belzona Facts:

The fast cure times allowed the mill to be operational within ten hours. Other grouts needed days for cure.

 
 

Photographs Description

  1. After surface preparation
  2. Pouring the Belzona slurry
  3. grouting almost complete
  4. Completed project
 
 