KHIA header

VOL XXVIII, NO 145

Belzona® Repairs Concrete Ramp

 
 

Industry:

Buildings & Structures (BSTR)

 
 

Application:

Floor Problem Areas (FPA)

 
 

Customer Location:

Bellingham, WA, USA

 
 

Application Date:

September 2014

 
 

Application Situation:

Cracking on an important loading ramp

 
 

Problem:

The foundation under the loading ramp had been undermined causing one concrete panel to crack which made a bump in the road for forklifts, which would then lose loads when hitting this joint.

 
 

Products:

Belzona 4111 (Magma Quartz)

 

Substrate:

Concrete

 
 

Application Method:

The appliaction was carried in accordance with Belzona Know-How System Leaflet FPA-1. The substrate was thoroughly cleaned and loose material removed.  A Teflon spacer was placed into the joint to separate adjacent panels thus avoiding a repeat of cracking that had occurred. The Conditioner was brush applied and Belzona 4111 was hand applied.

 
 

Belzona Facts:

The Customer had tried other materials with limited success and wanted a sure solution without a need to re-apply prematurely - hence Belzona was selected.

 
 

Photographs Description

  1. Area on forklift ramp for repair  
  2. Teflon spacer fit into joint to separate adjacent panels  
  3. Conditioner (seen around edge) and 4111 applied to repair area  
  4. The ramp repaired from a distance
 
 
  View PDF version  
 
 