KHIA headerKnow-How in Action

VOL XXV, NO 3

Belzona® Restores Hygiene Levels In Sweet/Candy Manufacturer

 
 

Industry:

General Industry (GIND)

 
 

Application:

Wall Problem Areas (WPA)

 
 

Customer Location:

Sweet/Candy Manufacturer, West Yorkshire, UK

 
 

Application Date:

June 2008

 
 

Application Situation:

Concrete Repair and coating required to internal walls.

 
 

Problem:

New Kitchen was being installed and required repairs to walls and a coating to be applied to ensure hygiene levels were met.

 
 

Products:

Belzona® 4141 (Magma Build) 

Belzona® 5111 (Ceramic Cladding) 

 

Substrate:

Concrete

 
 

Application Method:

Application was carried out in accordance with Belzona Know-How System Leaflets WPA-2 & 4. The damaged areas were repaired using Belzona® 4141 to ensure smooth surface for application of the Belzona® 5111 System. 

 
 

Belzona Facts:

Initially 1/3 of the kitchen areas were refurbished with the Belzona System. Since then the customer has been so pleased with the results that they plan to complete the rest of the kitchen areas.

 
 

Photographs Description

  1. Kitchen area to be coated
  2. Belzona® 5911 (Ceramic Conditioner) being applied
  3. Completed wall coating

 

 
Case study pic one

 

 
 Case study pic two

 

 
 

 

 
 Case study pic four

 

 
 
For more information about Belzona visit: www.belzona.com