| Belzona Tank Farm | | | Industry:Petrochemical (PETR) | | | Application:Tanks and Chemical Containment Areas (TCC) | | | Customer Location:Chemical Plant in South Alabama, USA | | | Application Date:August 1995 | | | Application Situation:Chemical containment area (5000 sq. ft.) | | | Problem:Harsh chemicals attacking existing substrate which was installed in 1993. | | | Products:Belzona® 4131 (Magma Screed)
Belzona® 4311 (Magma CR-1) | | | Substrate:Concrete and Polymeric Concrete | | | Application Method:The application was carried out in accordance with Belzona Know-How Leaflets TCC-9 and TCC-15. | | | Belzona Facts:The previous polymeric concrete repair material was damaged by chemical attack. The concrete was repaired and all areas protected. | | | Photographs Description
- View of damage to polymeric repair compound
- Application of Belzona® 4311 (Magma CR-1) in progress
- 5000 sq. ft. area protected
| |
| |