SCOOP TRAM WITH DAMAGED PIN BEARING BACK IN SERVICE WITH BELZONA AFTER ONE DAY

KHIA ID: 4188
Industry: Mining & Quarrying (MINQ)
Application: MPT-Mechanical Power Transmission (MPT)
Substrate: Steel
Customer Location: Salt mine, Germany
Application Date: November 2009
Products:

Belzona® 1821 (Fluid Metal) 


Problem: The severe corrosive and abrasive service conditions had led to metal loss on the articulated joint bearing pin, resulting in a relatively short life of the component.
Photograph Descriptions

Scoop tram before application Injection of the Belzona material Completed application After reassembly of the bearing

Application Situation
Scoop tram opeating in salt mine.
Application Method
The application was carried out in accordance with Belzona Know-How System Leaflet MPT-2.
Belzona Facts
Dismantling the pin housing for replacement would have been very time consuming and costly as the entire backing plate would have had to be detached. The Belzona forming technique not only allowed for the repairs to be completed in-situ after just one day but also significantly extended the life expectancy of the scoop tram bearing pin.