VOL XXVIII, NO 62

Belzona® Repairs Spalled Lintels On School

 
 

Industry:

Local Authorities & Municipalities (LOMU)

 
 

Application:

Wall Problem Areas (WPA)

 
 

Customer Location:

Primary School, Blackpool, UK

 
 

Application Date:

February 2012

 
 

Application Situation:

School exposed to local marine environment. A number of concrete lintels and sills, particularly those over-looking the playground and exposed to the prevailing winds and sea spray were in need of urgent refurbishment.  

 
 

Problem:

Pieces of concrete breaking away from the lintels were deemed a safety hazard and needed urgent solution to be completed during half term school holiday.

 
 

Products:

Belzona 4141 (Magma Build)

 

Substrate:

Concrete

 
 

Application Method:

Application was carried out in accordance with Belzona System Leaflet WPA-4. Areas were hammer tested to detect early signs of spalling and all loose concrete hacked off to leave solid substrate. Exposed rebar was abraded back to bright metal before building back to original profile with the Belzona 4141 system.

 
 

Belzona Facts:

The excellent non-slump characteristics allowed the rebuilding to be done quickly without the need for fixed shuttering. Cementitious repairs or replacement could not have been completed in the available time and would have led to un-necessary disruption to the school.

 
 

Photographs Description

1 & 2. Some of the damaged lintels and sills before application 3 & 4. Completed repairs

 
Case study pic one

 

 
 Case study pic two

 

 
 Case study pic three

 

 
 Case study pic four

 

 
 
For more information about Belzona visit: www.belzona.com