BELZONA REPAIRS HOLES WITH BULKFILL AND MAGMA QUARTZ

KHIA ID: 6324
Industry: Buildings & Structures (BSTR)
Application: FPA-Floor Problem Areas (FPA)
Substrate: Concrete
Customer Location: Truck Part Manufacturer, NC, USA
Application Date: June 2016
Products:

Belzona 4111 (Magma-Quartz)

Belzona 4124 (Bulkfill) 


Problem: Due to continious forklift traffic holes had formed causing an issue in operations. 
Photograph Descriptions

1. Preparing hole by removing loose material

2. After preparation

3. Bulkfilling with Belzona 4124

4. Top coated with Belzona 4111

Application Situation
Forklift traffic over control and expansion joint areas. 
Application Method
The holes were cleaned out and filled with Belzona 4124. Once the holes were filled, it was top coated with Belzona 4111. FPA-1 System Leaflet was followed.
Belzona Facts
Customer saved a lot of money because there is a tunnel under the areas where the repair was done. Concrete was an option, but it would be a long and costly repair, and would eventually fail again. It took 1 day of labor to do the work. This Belzona system was used because it is proven to work and last a long, long time.