Belzona® 7111 Aligns New Industrial Equipment

 
 

Industry:

General Industry (GIND)

 
 

Application:

Gaskets, Seals and Shims (GSS)

 
 

Customer Location:

Manufacturing Plant, FL, USA

 
 

Application Date:

August 2016

 
 

Application Situation:

New factory expansion needed chocking of three recently installed machinery. Leveling of the equipment was critical as well as preventing water with salt residues from penetrating beneath the bases.

 
 

Problem:

On going construction on and around these equipment could not be stopped. Application had to be performed diligently and in harmony with other construction activities. The depth of the pours ranged between 1.5in to 3in.

 
 

Products:

Belzona 7111

 

Substrate:

Steel base, concrete floor

 
 

Application Method:

The application was carried out in accrodance with the Belzona Know-How System Leaflet GSS-12. 

 
 

Belzona Facts:

The application was carried out in less than a day with no interruption to the operation of the plant. 

 
 

Photographs Description

1. View of the gap needed to be filled.

2. Temporary wood dam and expansion joint.

3. Pouring of first layer.

4. After dam removal.

 