Belzona® Keeps The Lights Shining

 
 

Industry:

Power (POWR)

 
 

Application:

Valves, Pipes and Fittings (VPF)

 
 

Customer Location:

Primary Electricity Sub Station, UK

 
 

Application Date:

June 2006

 
 

Application Situation:

A Porcelain Transformer Bush was being replaced in the Substation.

 
 

Problem:

Mis-alignment into steel turret occurred causing the Oil in the transformer to seep out and create a live oil leak.

 
 

Products:

Belzona® 1161 (Super UW-Metal)
 

Substrate:

Porcelain and Steel

 
 

Application Method:

Application was carried out in accordance with a modified version of Belzona Know-How System Leaflet VPF-11a.

 
 

Belzona Facts:

While the transformer was being changed an emergency generator had been hired at a cost of £50,000 per week. To change the transformer would mean at least a further 4 weeks work and hire charge, assuming a spare transformer was available. Belzona repair took 12 hours at a cost of £1,000.

 
 

Photographs Description

  1. Finding the leak
  2. Preparing the substrate
  3. Applying the Belzona® 1161
  4. The finished transformer in-situ
 
Case study pic one

 

 
 Case study pic two

 

 
 Case study pic three

 

 
 Case study pic four

 

 
 