VOL XXIII, NO 7

Belzona Anchors The Track

 
 

Industria:

General Industry (GIND)

 
 

Áreas Know-How:

Floor Problem Areas (FPA)

 
 

Cliente / ubicación:

Steel Plant, North Alabama USA

 
 

Fecha de aplicación:

2002

 
 

Situación de aplicación:

Grout had failed around the blast furnace rails

 
 

Problema:

Grout had to achieve high compressive strength in short outage time

 
 

Productos:

Belzona® 4111 (Magma Quartz)
 

Substrato:

Concrete and Steel

 
 

Método de aplicación:

Application was carried out in accordance with modified Belzona Know-How System Leaflet FPA-10. The old grout was removed and the rail was alligned and shimmed. A slurry mix of Belzona® 4111 was poured the length of the tract.

 
 

Hechos Belzona:

The fast cure times allowed the mill to be operational within ten hours. Other grouts needed days for cure.

 
 

Descripciones de fotografías

  1. After surface preparation
  2. Pouring the Belzona slurry
  3. grouting almost complete
  4. Completed project
 
Case study pic one

 

 
 Case study pic two

 

 
 Case study pic three

 

 
 Case study pic four

 

 
 
Para obtener más información acerca de los productos Belzona visite: www.belzona.com