| Belzona Rapid Floor Repair | | | Industry:General Industry (GIND) | | | Application:Floor Problem Areas (FPA) | | | Customer Location:Box manufacturer, Montgomery, Alabama USA | | | Application Date:January 2007 | | | Application Situation:Concrete floor in production area | | | Problem:Hole in floor creating problem for fork lift drivers loading and unloading cardboard for box manufacture. | | | Products:Belzona® 4911 (TX Conditioner)Belzona® 4131 (Magma Screed) | | | Substrate:Concrete | | | Application Method:Application was carried out in accordance with Belzona Know-How System Leaflet FPA-1. | | | Belzona Facts:The alternative was to saw cut concrete and pour new concrete. That would be more costly because of labor and down time in the area. It was possible to drive over the Belzona applied in morning that night. | | | Photographs Description- Removed concrete from hole
- Belzona® 4911 being applied
- & 4. Finished application
| |
| |