KHIA headerKnow-How in Action

VOL XIX, NO 1

Belzona® 4111 (Magma-Quartz) Keeps Production On Track

 
 

Industry:

General Industry (GIND)

 
 

Application:

Floor Problem Areas (FPA)

 
 

Customer Location:

Animal food manufacturer - Missouri USA

 
 

Application Date:

November 2004

 
 

Application Situation:

Loading dock - stainless steel plate

 
 

Problem:

Fork lift traffic damaged stainless steel plate being bent by fork lift trucks pushing pallets into it and lifting it up. Needed a solution to avoid further damage.

 
 

Products:

Belzona® 4111 (Magma-Quartz)

 

Substrate:

Concrete & stainless steel

 
 

Application Method:

Application was carried out in accordance with Belzona Know-How System Leaflets FPA-5 and FPA-10.

 
 

Belzona Facts:

Very little time to consider alternatives, which would have been costly as the facility operates 24/7. Also, a government inspection was on the near horizon, and this problem could have caused the facility to fail an inspection. The use of Belzona® 4111 (Magma-Quartz) allowed the facility to quickly and very cost effectively keep production on track.

 
 

Photographs Description

  1. Close up of the problem
  2. Surface prepped
  3. Ready for traffic
 
Case study pic one

 

 
 Case study pic two

 

 
 Case study pic three

 

 
 Case study pic four

 

 
 
For more information about Belzona visit: www.belzona.com