BELZONA ANCHORS THE TRACK
Industry: General Industry (GIND)
Application: FPA-Floor Problem Areas (FPA)
Substrate: Concrete and Steel
Customer Location: Steel Plant, North Alabama USA
Application Date: 2002
Products: Belzona® 4111 (Magma Quartz)
Problem: Grout had to achieve high compressive strength in short outage time
Photograph Descriptions
- After surface preparation
- Pouring the Belzona slurry
- grouting almost complete
- Completed project
Application Situation
Grout had failed around the blast furnace rails
Application Method
Application was carried out in accordance with modified Belzona Know-How System Leaflet FPA-10. The old grout was removed and the rail was alligned and shimmed. A slurry mix of Belzona® 4111 was poured the length of the tract.
Belzona Facts
The fast cure times allowed the mill to be operational within ten hours. Other grouts needed days for cure.