BELZONA PUMP REBUILD
Industry: Water / Wastewater (WATR)
Application: CEP-Centrifugal Pumps (CEP)
Substrate: Cast iron
Customer Location: Water Utility, Oklahoma USA
Application Date: March 2008
Products:
Belzona® 1311 (Ceramic R-Metal)
Belzona® 1341N (Supermetalglide)
Problem: Many of the pumps have never been rebuilt and severe pitting was present. In some cases, it went almost through the casing.
Photograph Descriptions
- Pump casing after grit blasting
- Deep pitting repaired with Belzona® 1311
- First coat of Belzona® 1341N applied
- Second coat applied to complete the application
Application Situation
Old split case pumps dating back to 1960.
Application Method
Application was carried out in accordance with Belzona Know-How System Leaflets CEP-1, CEP-3, and CEP-5.
Belzona Facts
It is substancially more cost-effective to rebuild versus replace. The utility can do a quick turnaround in repairing these units themselves in 2 days and for $800 in material. Efficiency is restored and enhanced and will be maintained for longer than untreated pumps.