Problem: Asphalt, used to replace lead flashings in gutters, had failed allowing water ingress into the four boarding house buildings. Several attempts to repair the asphalt had failed. The school required a solution to be cold applied so allowing them to remain in use.
Photograph Descriptions
- Asphalt replacement of lead flashing showing heavy UV degradation and breakdown
- View of roof showing gutter and asphalt replacement of lead flashing
- Belzona® 3131 successfully applied to area of flashing where substrates are slate, asphalt & stone
- Finished Belzona® 3131 application to gutters and flashing.
Application Situation
School had been suffering water ingress via lead flashings & gutters on four boarding house roofs.
Application Method
The application was carried out in accordance with modified versions of Belzona Know-How System Leaflets RPA-6 & RPA-8.
Belzona Facts
The Belzona solution was carried out over two weeks. Belzona® 3131 bonding to all of the substrates meant that the old asphalt did not require complete removal which could have led to damage to the slate tiles. The results were a complete success allowing the school continued use of the boarding houses. To replace the damaged asphalt with traditional lead work would have been over budget & involved hot work stopping the use of the boarding houses & the summer school events.